Century Bliss Construction Status


Featured Image of Century Bliss Construction Status

Century Bliss construction status is now in the new launch stage, and construction has just started. All government approvals are in place, and the RERA plan approval was received. The project officially launched on 1st May 2026. Early site work has started on the ground. The model apartments are ready, and the site office is fully operational. Earthwork and levelling started in May 2026, and it will finish by 27-12-2026.

Current Focus Areas


  • Planning the full layout
  • Marking the land for roads
  • Deciding the main entry/exit gates
  • Planning boundary walls
  • Doing fencing details
  • Designing all the internal roads inside the project

The early steps will help to make construction well-organised when tower work begins.

RERA-Filed Construction Timeline


Century Real Estate has filed a detailed construction schedule with RERA at registration. It will give full transparency on every stage of the building.

Sub Structure Work

  • Earth work & levelling: 01-04-2026 to 27-12-2026
  • Foundation footing: 28-10-2026 to 29-01-2027
  • Up to plinth level: 16-11-2026 to 17-10-2027
  • Sub structure flooring (parking level): 09-03-2027 to 25-09-2027
  • Retaining wall: 09-03-2027 to 25-09-2027

Super Structure Work

  • RCC framed structure: 07-08-2027 to 29-03-2029
  • Masonry construction: 22-10-2028 to 19-07-2029
  • Plastering: 20-04-2029 to 25-01-2030
  • Doors, and windows: 26-11-2029 to 11-11-2030
  • Water supply and electrification: 01-02-2030 to 07-04-2031
  • Flooring and tiling: 02-05-2030 to 29-10-2030
  • Railing and grill fixing: 25-01-2030 to 15-05-2030

Finishing Work

  • Electrical, water and sanitary finishing: 19-07-2029 to 11-03-2031
  • Painting Work: 26-12-2029 to 11-11-2030
  • Fire fighting systems: 16-12-2029 to 20-01-2031
  • Elevation work: 26-03-2030 to 19-02-2031
  • Landscaping and external works: 15-01-2030 to 11-12-2030

Project Readiness and Planning


For Century Bliss, all details like tower positions, apartment sizes, and layouts are already finalised.

The RERA-verified carpet areas are:

  • 1 BHK: 550 to 824 sq. ft.
  • 2 BHK: 721 to 1111 sq. ft.
  • 3 BHK: 890 to 1664 sq. ft.
  • 4 BHK: 1648 to 2137 sq. ft.

The builder is making sure that everything is ready before starting the construction work. This planning helps to avoid delays and keeps the full project on schedule. When planning is done, construction becomes faster.

Latest Construction Updates for Buyers


Century Real Estate builder believes in keeping buyers and investors informed about the latest project status. Construction updates are shared regularly through the official website and direct messages from the sales teams. These construction updates help buyers know how the project is moving now and how close Century Bliss is to nearing completion.

FAQs


1. What is the possession date that is given for Century Bliss project?

The possession date is confirmed for April 2031 without any delay.

2. How can I know the latest construction stages?

It can be tracked by visiting this page or by contacting the sales team.

3. What is the latest construction status of Century Bliss as of June 2026?

The project launched on 1 May 2026, and construction has started. The model apartment is ready to view, and the site office is fully operational.