Century Bliss Project Schedule AS of RERA


Featured Image of Century Bliss Project Schedule As Of Rera

Century Bliss Project Schedule shows the sub structure, super structure, finishing works, internal infrastructure, amenities, common areas, and external infrastructure. It helps buyers to get a clear understanding of the project and the completion timeline.

The details of substructure and its completion timelines are as follows,


Sl No Project Work From Date To Date
1 Earth work and other leveling preparation work 01-04-2026 27-12-2026
2 Foundation footing work 28-10-2026 29-01-2027
3 Upto Plinth Level 16-11-2026 17-10-2027
4 Sub structure flooring (Parking Floor, more than 1 floor below general ground level) 09-03-2027 25-09-2027
5 Retaining wall (All types) 09-03-2027 25-09-2027

The details of super structure and its completion timelines are as follows,


Sl No Project Work From Date To Date
1 RCC or MS Framed structure 07-08-2027 29-03-2029
2 Masonry 22-10-2028 19-07-2029
3 Plastering inside , outside & Ceiling 20-04-2029 25-01-2030
4 Joinery: Doors, Windows, Ventilators etc 26-11-2029 11-11-2030
5 Basic work of Water supply, Sanitary 01-02-2030 07-04-2031
6 Dado ing, Skirting, Flooring, Tiles work (All the types) 02-05-2030 29-10-2030
7 Railing and Grill fixing 25-01-2030 15-05-2030

After this the Finishing Works (Fitting and Fixtures) will be done and its timeline is as follows,


Sl No Project Work From Date To Date
1 Water supply and Sanitary Finishing 19-07-2029 11-03-2031
2 Painting 26-12-2029 11-11-2030
3 Fire prevention & fire fighting fitting and fixture with network 16-12-2029 20-01-2031
4 Weather Proof work(tile, concrete) 04-04-2030 30-11-2030
5 Wardrobe, Showcase, Kitchen cabinet, Puja work
6 Elevation work 26-03-2030 19-02-2031
7 Internal and External work including area as per sanctioned drawings 15-01-2030 11-12-2030

Then the Internal Infrastructure work will start and its timeline are as follows,


Sl No. Work Is Applicable?
1 Water Supply Yes
2 Sewage and Drainage System Yes
3 Water saving/rain water harvesting/recharge of ground water Yes
4 Energy management Yes
5 Fire protection and fire safety needs Yes
6 Solid waste management and disposal Yes
7 Emergency Evacuation services Yes

Then the External Infrastructure work will start and its timeline are as follows,


Sl No. Work Is Applicable?
1 Water Supply Yes
2 Internal Roads & Footpaths Yes
3 Sewage and Drainage System Yes
4 Electricity supply transformer and substation Yes
5 Solid waste management and disposal Yes
6 Emergency Evacuation services Yes
7 Storm water drains Yes
8 Use of renewable energy Yes
9 Water conservation/rain water harvesting/recharge of ground water Yes
10 Fire protection and fire safety requirements Yes
11 Sewage Treatment Plant (STP) Yes
12 Parks & Tree planting Yes
13 Street Lighting Yes

The list of amenities in the project is as follows,


Sl No. Work Area (Sq Mt)
1 Electricity 169.63
2 Smart Home Automation
3 CCTV Surveillance 0.0
4 Club House 1451.18
5 Community Hall 128.81
6 Outdoor Sports facility 554.74
7 Indoor Sports facility 241.89
8 Swimming Pool 144.0
9 Gym 203.53
10 Parks 1780.09
11 Power Backup 95.21
12 Piped Gas
13 Water and Sanitation 886.46
14 Air Conditioning

The Common Areas and the total area os the common spaces are as follows,


Sl No. Work Area (Sq Mt)
1 Staircases 1670.55
2 Lifts 712.81
3 Corridor/Lobbies 2583.65
4 Fire escapes 1670.55
5 Common entrance and exit for the building/common portico/foyer/verandah 425.7
6 Basement 19066.32
7 Terrace 236.98
8 Outer Wall 3700.56
9 Open parking areas
10 Provision for lodging of management staff and security staff
11 Water conservation and renewable energy 0.0
12 Common storage spaces

These details help buyers understand what amenities are offered in the project, along with the common areas and their total area. With this, buyers can get a clear understanding of the whole project space.

Frequently Asked Questions


1. Will the project be completed on time?

Yes, the project will be completed on correct time, and there will not be any delay.

2. What happens if there is any delay in the project?

The builder has planned deadlines for each task and has planned to finish on time.

3. How can buyers know about the project schedule?

Buyers can know about the project schedule from the official website of the project.